Site C workforce jumped by 1,000 in June

The Site C workforce grew by more than 1,000 in June, as construction ramped up after a two-month shutdown during the COVID-19 pandemic.

BC Hydro reported 4,324 workers for the month, which it said reflected its May 14 decision to ramp construction activities back up at the dam site. A significant portion of construction was suspended in mid-March due to the pandemic, and the workforce was slashed by more than half as construction wound down primarily on the powerhouse and spillways.

article continues below

Of the June workforce, around 19% was local, with 608 Peace region residents employed as construction and non-construction contractors, up 217 month-over-month.

Locals made up 23% of the construction and non-construction workforce total of 3,580 workers, which includes work at the dam site, on transmission corridors, reservoir clearing, public roadworks, and camp accommodations.

There were 2,417 B.C. workers, or 68%, working for construction and non-construction contractors, and in engineering and project team jobs.

site-c-workforce-june2020
Site C workforce numbers, June 2019 to June 2020. Source: BC Hydro

BC Hydro reported 147 apprentices for the month, up 86 from May, as well as 305 indigenous workers (+116), and 426 women workers (+83) on the project.

There were three temporary foreign workers employed in specialized positions (no change), and another 49 managers and other professionals working under the federal international mobility program (no change). 

As of Aug. 6, there were 1,478 workers reported at the camp outside Fort St. John, including one in self-isolation.

BC Hydro says a worker who tested positive for COVID-19 in July was cleared to leave self-isolation. No other cases have been reported at the project.

Email Managing Editor Matt Preprost at editor@ahnfsj.ca.

© Copyright Dawson Creek Mirror News

Comments

NOTE: To post a comment you must have an account with at least one of the following services: Disqus, Facebook, Twitter, Google+ You may then login using your account credentials for that service. If you do not already have an account you may register a new profile with Disqus by first clicking the "Post as" button and then the link: "Don't have one? Register a new profile".

The Dawson Creek Mirror welcomes your opinions and comments. We do not allow personal attacks, offensive language or unsubstantiated allegations. We reserve the right to edit comments for length, style, legality and taste and reproduce them in print, electronic or otherwise. For further information, please contact the editor or publisher, or see our Terms and Conditions.

comments powered by Disqus