Photo Gallery on Dawson Creek Mirror
Site C Construction - February 2019
A look at Site C dam construction on the Peace River outside Fort St. John, February 2019. BC Hydro Photos
1/9

A worker assembles one of 405 towers that will hold up two 75-kilometre, 500-kv transmission lines. The lines will connect power from Site C to BC Hydro's transmission system through the Peace Canyon switchyard.
Photo By
bc hydro

On-site concrete batch plant, February 2019.
Photo By
bc hydro

Excavation on the foundation for the three concrete spillways on the south bank of the Peace River, February 2019.
Photo By
bc hydro

View of the powerhouse and main service bay under construction on the south bank of the Peace River, February 2019.
Photo By
bc hydro

Workers install draft tube framework for generating unit #1. After going through the turbine, water is diffused in the diffused in the draft tube before re-entering the river, February 2019.
Photo By
bc hydro

A view of the unite #3 draft tube formwork and laydown area, where equipment and materials are stored, February 2019.
Photo By
bc hydro

Workers review drawings for the main service bay area, February 2019.
Photo By
bc hydro

Rebar is installed in the main service bay before concrete is poured into the framework, February 2019.
Photo By
bc hydro

Once operational, water enters turbines through large spiral-shaped pipes known as spiral cases, which are made of formed and welded steel plates. The bottom section of a spiral case is welded by a robot at the on-site manufacturing shop, February 2019.
Photo By
BC Hydro